River Delta Unified School Bonds
On November 2020, the voters of Sacramento, Solano and Yolo Counties who reside in the River Delta Unified School District, voted to pass both School Facilities Improvement District's General Obligation Bonds. These Bonds will provided needed repairs and modernization project in the District.
On April 13, 2021 the Board of Trustees authorized the consolidation of the two separate Bond Oversight Committees for Measure J and Measure K and appoint members from the two separate committees to the new consolidated Committee.
The Bond Oversight Committee is seeking additional members to join. If you are interested in being a part of the committee, please see the attached application. (Application)
COMPLETED BOND PROJECTS
-
New marquee purchased, installed and operating at D.H. White Elementary Elementary School
-
New marquee purchased, installed and operating at Isleton Elementary School
-
New marquee purchased, installed and operating at Riverview School
-
New marquee purchased, installed and operating at Walnut Grove Elementary School
-
Fire Alarm upgrade at Walnut Grove Elementary
-
Walnut Grove Exterior Lighting
-
Roof project completed at Bates Elementary
-
Roof project completed on D.H.White office builing
-
Roof project completed on D.H.White building A
-
Roof project completed on Delta High School Office North building
-
Roof project completed on Rio Vista High Cafeteria, Library and Office buildings
BOND PROJECTS UP FOR BID
New Fencing at Isleton Elementary and Rio Vista High School
Riverview Middle School Modernization
• For information and to obtain a copy of bid documents contact the District’s Construction Manager, RGM Kramer, Inc. 925-671-7717
PLANNED BOND PROJECTS
• HVAC repairs and upgrades at multiple school sites
• Cafeteria Modernization at Clarksburg Middle and Delta High School
• Replace modular buildings at D.H. White Elementary School
• Replace Administrative building at D.H. White Elementary School
• Update Administrative building at Isleton Elementary
• Modernization of Building A at Riverview Middle School